Skip Navigation LinksGETTING ELECTRICITY

 GETTING ELECTRICITYGE procedure_1 280518.png

 GE DWCP.png


S: Adakah OP (Sijil Kesiapan Bangunan) diperlukan untuk mendapatkan bekalan elektrik?
Q: Is OP (Occupation Permit) required to obtain electricity
J: Ya, OP diperlukan semasa menghadapkan borang permohonan (prosedur 3).
A: Yes, OP is required during initial submission (procedure 3)

S: Bolehkah agensi kerajaan menepati TPOR 7 hari bagi proses 1 memandangkan proses berkenaan melibatkan 2 skop kerja?
Q: Will the government agencies able to meet the 7 days TPOR for procedure 1 since it involves two different scope of work?
J: TPOR 7 hari adalah komitmen daripada Kementerian Pembangunan.  Statistik TPOR boleh dilihat dalam laman web Jabatan peratus proses yang menepati TPOR.
A: 7 days TPOR is a commitment by Ministry of Development.  Statistics of each procedures is updated weekly in this page

S: Apakah proses untuk mendapatkan bekalan sementara untuk kerja-kerja pengujian pendawaian dan berapa lama bekalan elektrik sementara diberikan oleh Jabatan?
Q: What are the procedures for getting temporary supply for the purpose of testing and how long will the temporary supply be give?
J: Pemborong/Konsultan hendaklah menghadapkan surat rasmi ke Jabatan.  Tempoh kelamaan bekalan diberikan tertakluk kepada premis yang dipohonkan.
A: Consultants/Contractors need to submit a letter to the Department.  Period of temporary supply is based on the application.

S: Apakah proses mendapatkan bekalan elektrik melibatkan bekalan daripada BPMC?
Q: What is the procedure for getting electricity which involves supply from BPMC?
J: Pihak Jabatan mencadangkan agar pemborong/konsultan berurusan terus dengan BPMC
A: The Department suggests the contractors/consultants to consult BPMC directly

S: Adakah vendor meter prabayar maklum dengan prosedur baru mendapatkan meter?
Q: Are meter vendors aware of the new procdures?
J: Syarikat Wadura dan EngiCon Sdn Bhd (vendor meter prabayar) sudah maklum dengan proses baru ini.
A:Syarikat Wadura and EngiCon Sdn Bhd are aware of the new procedures.

S: Bolehkan pembayaran 'connection charges' dibuat awal sebelum prosedur 3?
Q: Can the connection charges be paid before procedure 3?
J: Pembayaran 'connection charges' hanya dapat dibayar dalam prosedur 3 setelah borang permohonan dihadapkan dengan lengkap.
A: Connection charges can only be paid when submitting complete application form.

S: Adakah penggunan prepaid CT meter dimestikan oleh Jabatan?
Q: Is the use of Prepaid CT meter made compulsory by the Department?
J: Bagi permohonan 101A-400A, prepaid CT meter dengan built in modem adalah dimestikan.
A: Prepaid CT meter is compulsory for 101A-400A application.

S: Pemborong/Konsultan memohon tatacara (guideline) bagi pembekalan kabel HT memandangkan pada masa ini Jabatan tidak lagi membekalkan kabel berkenaan. 

Adakah ia melibatkan semua permohonan ataupun Jabatan akan membekalkan kabel berkenaan sekiranya kabel yang diperlukan terlalu panjang?
Q: Is the supply of HT cable by applicant involves all application?
J: Pada dasarnya, semua permohonan yang memerlukan kabel HT akan ditanggung sendiri oleh pemaju mulai 1 Januari 2016.
A: Starting from 1st January 2016, HT cable will be provided by the developer

S: Adakah Jabatan/Agensi berkenaan bercadang untuk menyediakan online tracking bagi proses mendapatkan elektrik?
Q: Does the Department provide online tracking for getting electricity?
J: Pada masa ini tidak ada
A: Not the moment

S: Berapakah caj penyambungan bekalan elektrik?
Q: What are the connection charges for getting electricity?
J: Sila rujuk   Connection Charges.pdf    untuk maklumat lebih lanjut
A: Please refer Connection Charges.pdf   for more information

S:  Apakah borang-borang yang perlu dihadapkan bagi Langkah 1 Mendapatkan Elektrik?
Q: What are the forms to be submitted for Step 1 Getting Electricity?
J: Borang Survey Contractor dan Borang Permit to Dig
A: Contractor Survey form and Permit to Dig form

S: Apakah perkara yang perlu dibuat sebelum memulakan kerja-kerja bagi Langkah 2 Mendapatkan Elektrik?
Q: What are needed to be done prior to doing works for Step 2 Getting Electricity?
J: Pemborong dikehendaki mengisi Borang DCS 009 dan disahkan oleh pemilik rumah/bangunan
A: Contractors have to fill in DCS 009 form and to be verified by house/building owner

S: Apakah borang yang perlu digunakan untuk membuat laporan pengujian pendawaian dalalm Langkah 2 Mendapatkan Elektrik?
Q: What is the form to be used for reporting electrical wiring installation test in Step 2 Getting Electricity?
J: Jurutera Professional hendaklah menggunakan Borang Pengujian BS7671 untuk disertakan dengan surat pengesahan pengujian pendawaian
J: Professional Engineers have to use the  BS7671 Test Forms and attached them with their testing certification letter

S: Bagaimanakah memohon bekalan sementara yang melebihi 6 bulan?        

Q: How do I apply for temporary supply which is more than 6 months?

J: Pemohon boleh memuat turun Borang Bekalan Sementara dan menghadapkan ke Jabatan secara manual untuk mendapat kebenaran.   

A: Applicants can download the Temporary Supply Form and submit to the Department manually to get approval.


KPI FOR GETTING ELECTRICITY IN BRUNEI DARUSSALAM AS OF WEEK 32, 2019

Efficiency
Total no. of application​Brunei Darussalam​110
​​Bandar Seri Begawan19
Average time to complete (calendar days)​Brunei Darussalam​11
​​Bandar Seri Begawan7
​No.​ProcedureAreaTime to complete
(calendar days)

Associated Cost
(BND)

Average time to complete
(calendar days)
​No of application meeting target to date
(%)
​FY 2019
(%)
​1
An approve electrical contractor submits application for approval of the tapping point to the Department of Electrical Services .

Apply for a Permit to Dig throught onebiz.business.gov.bn should excavation work be needed.

 
DES  to release letter for purchase of prepaid meter.
​Brunei Darussalam

 

 

 

 

5

 

 

 

 

0

4
91
95
Bandar Seri Begawan​3
100
100
​2

Excavation and underlying works can be done immediately.

​Electrical prepayment meter is procured and installed by an authorized vendor.

Testing can be done immediately.

​Brunei Darussalam

 

 

​8

 


 Based on quotes by contractors

6
92
96
​Bandar Seri Begawan​3
100
100
​3

The client's appointed electrical contractor pays the Connection Charges to the Department of Electrical Services on behalf of the client.

Final application submission with relevant documents to obtain approval for permanent supply.

​Brunei Darussalam

 

 

 

​2

 

 

* Based on subscribed capacity (kVA)
e.g 140 kVA connection charges is $1,650

1
94

97

​Bandar Seri Begawan​1
90
95


      CHART WEEK 32A EODB 2019.png

*Please submit your complaints if we do not meet the set target duration for the above procedures.

  
  
Message
Response
  
  
agen bandar togelEfficiency
Open15/06/2019 01:32 PM
agen bandar togel onlineEfficiency
Bagaimana jika kami memberi tahu agen togel ada cara sederhana untuk meningkatkan penjualan online memperkuat basis klien Anda, dan memberi dorongan kepada merek Anda? Itu semua dimungkinkan dengan membangun aplikasi seluler untuk toko agen togel http://agen4d.batcave.net/ online Anda. Sebagai hasil dari meningkatnya penggunaan ponsel cerdas dan aktivitas aktif, nilai yang diproyeksikan dari pasar ritel seluler diperkirakan bandar togel mencapai miliar di seluruh dunia.

Ini menunjukkan bahwa banyak pembeli online menghargai keunggulan aplikasi bandar togel untuk seluler mengambil alih pasar, mendapatkan banyak pengguna dan mendapatkan keuntungan besar. Dengan mempertimbangkan perkembangan bandar togel https://adminototo-vcjm.envatosites.com/ online yang menguntungkan dalam e-commerce seluler, ada titik balik agen togel yang mendekat: kemungkinan perangkat seluler akan segera melampaui desktop sebagai perangkat utama untuk ritel online .

Di babak pertama rasio antara penggunaan desktop dan seluler untuk  mulai bergeser, dengan agen togel menjadi titik kritis online pertama. Melihat bahwa banyak negara mengikuti arah yang sama, pentingnya aplikasi seluler untuk pengecer agen togel
https://admintoto.8b.io/ bandar togel online terlihat jelas. Dan untuk alasan yang bagus. Seperti yang dapat kita lihat dari grafik di bawah ini, jumlah pengguna bandar togel yang lebih suka berbelanja di perangkat seluler terus bertambah, semakin memperkuat kebutuhan untuk pengembangan online di internet
Open12/06/2019 03:56 PM
agen poker bandar cemeEfficiency
Penjual bandar ceme harus menghadapi kenyataan bahwa agen poker tidak bisa mengendalikan citra online ada sedikit peluang bagi Anda untuk merek produk sebagai milik Anda. Tidak seperti platform agen ceme https://pokerceme.pagexl.com/ agen poker sendiri tidak memiliki etalase untuk merek. Jika Anda tidak memenuhi barang sendiri, pengiriman bahan tidak dapat dicap ke perusahaan unik Sebagai gantinya, branding pasar adalah agen poker https://cemepoker.netlify.com/ online yang utama dan pusat bagi pelanggan. Beberapa pengecer online tidak ingin meluangkan waktu, upaya, dan sumber daya untuk melakukan branding sendiri. Bagi agen poker yang lain, ini adalah kesempatan bandar ceme  yang terlewatkan untuk memperkuat citra merek Anda dengan pelanggan online Anda di internet.
Open09/06/2019 01:51 PM
SyaiEfficiency
power outage at kg mata mata spg 52 is not yet completed from morning,  heard that they’re changing the generator and affecting all the surrounding areas even worst during sungkai hours. There is no proper communication  either provided to us on how long will this take and just leaving us in the dark. Please do something about this! we’ve been calling 123 numerous times, but no answer cant be given to us. We understood their role is only to coordinate, but please DES , do give information to them so that they can give us the right information and answer on how long will this take and please do your work efficiently.

Open01/06/2019 07:22 PM

submit_complaints.pngviewall.png
 

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Power Supply Reliability
No.​Indicator​Target​YTD
(until 13/08)
​Full Year Estimate
FY(2019)
​1​Power outage > 1 hour​52
36
59
2​​System average interruption Duration Index (SAIDI)​ ​ ​
​i. Transmission (Brunei Darussalam)
13.04
4.06
6.60
​ii. Distribution (Brunei Darussalam)
17.65
12.82
20.83
i​ii. Distribution (BSB Municipal)
11.92
7.16
11.64
3​System average interruption Frequency Index (SAIFI)​ ​ ​
i. Transmission (Brunei Darussalam)
0.33
0.09
0.15
ii. Distribution (Brunei Darussalam)
0.26
​0.22
0.36
i​ii. Distribution (BSB Municipal)0.21
0.10
​0.16


Definition:
SAIDI - System Average Interruption Duration Index is the average outage duration for each customer served (mins/ customer)
SAIFI - System Average Interruption Frequency Index is the average number of interruptions that a customer would experience (interruption/ customer)

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------




submit_complaints.png viewall.png